Comparative Analysis of Project Completion Forecasting Using Earned Value Management, Earned Schedule, and Program Evaluation and Review Technique

Authors

  • Kevin Ardian Krisanto Civil Engineering Master Program, Tarumanagara University, West Jakarta
  • Mega Waty Civil Engineering Master Program, Tarumanagara University, West Jakarta

DOI:

https://doi.org/10.51988/jtsc.v7i3.607

Keywords:

Construction Project, Earned Value Management, Earned Schedule, Program Evaluation and Review Technique, Schedule Performance

Abstract

This study evaluates schedule performance and forecasts the completion time of a restaurant construction project in the PIK 2 area by integrating Earned Value Management (EVM), Earned Schedule (ES), and the Program Evaluation and Review Technique (PERT). Unlike previous studies that apply these methods separately or through pairwise comparisons, this study integrates deterministic performance evaluation and probabilistic schedule forecasting to provide a comprehensive framework for project control. The project was evaluated at week 13 of a planned 37-week duration. EVM produced a Schedule Variance (SV) of ?Rp1,051,310,568 and a Schedule Performance Index (SPI) of 0.774, forecasting completion at week 48. ES generated a Time Variance (SV(t)) of ?4.44 weeks and an SPI(t) of 0.659, projecting completion at week 56. PERT estimated an expected project duration of 122.67 days and forecast completion at week 42 without acceleration and week 40 with acceleration at a 95% confidence level. The findings demonstrate that integrating EVM, ES, and PERT provides complementary insights for monitoring project performance, quantifying schedule uncertainty, and improving completion forecasting.

References

Kerzner, H. (2025). Project Management: A Systems Approach To Planning, Scheduling, And Controlling (14th Edition) (14th ed.). John Wiley & Sons.

Melkisedek, J. & Jin, O, F. (2024). Analisis Prediksi Durasi Akhir Proyek dengan Metode Earned Value dan Earned Schedule. JMTS: Jurnal Mitra Teknik Sipil, 7(4), 1377–1388. https://doi.org/10.24912/jmts.v7i4.30380

Tangtobing, R. F. F., & Waty, M. (2023). Penerapan Metode Earned Value dan Earned Schedule Pelaksanaan Proyek Rumah Sakit X Di Bandung. JMTS: Jurnal Mitra Teknik Sipil, 6(2), 237–248.

Agus Winarto, D., Ratnaningsih, A., & Soetjipto, W. (2023). Analysis of Project Performance and Completion Time Using EVM and CPM-PERT Methods (Case Study of Road Reconstruction Project). International Journal of Sciences: Basic and Applied Research (IJSBAR), 70(1), 269–280. https://gssrr.org/index.php/JournalOfBasicAndApplied/index

Andreas, A., Tinumbia, N., & Anggraini, E. (2023). Construction Project Control Analysis Using Earned Value Management, Earned Schedule Management, Earned Duration Management (Case Study: Highrise Building Project in Jakarta). Jurnal Infrastruktur, 9(2), 87–98.

Karlina, D., Rahmawati, S., Hutagalung, R. A., & Amin, M. (2025). Model dan Metode Integrasi Biaya dan Jadwal Dalam Manajemen Proyek: Sebuah Systematic Literature Review Periode 2020–2025. Jurnal IPTEK, 9(22).

Lipke, W. (2014). Introduction to Earned Schedule. In PM World Journal Introduction to Earned Schedule: III. www.pmworldlibrary.net

Widowati, E. D., & Resita, A. M. (2025). Project Duration Forecasting Methods Using EVM and ESM For A Double-Track Railway Project in Comparison. Jurnal PenSil, 14(3), 456–472. https://doi.org/10.21009/jpensil.v14i3.59154

Wilanata, C., & Waty, M. (2024). Analisis Metode Earned Value Untuk Prediksi Penyelesaian Proyek Konstruksi Apartemen X Di Tangerang. JMTS: Jurnal Mitra Teknik Sipil, 7(3), 873–884.

Lim, W. H., & Gondokusumo, O. (2025). Perbandingan estimasi durasi proyek dengan metode earned schedule dan metode earned duration management. JMTS: Jurnal Mitra Teknik Sipil, 8(3), 635–644.

Rifqi, M., Shiddiq, F., Maskur, A., & Hartati, G. (2025). Evaluasi Pengendalian Waktu Menggunakan Metode Earned Value Management (EVM) (Studi Kasus: Konstruksi Fisik Pembangunan Gedung Parkir Sepeda Motor). Media Ilmiah Teknik Sipil, 19(1), 22–29.

Fadjar, A., Ali, A., & Setiawan, A. (2023). Estimating House Construction Completion Time With Probabilistic Activities Duration Using The Program Evaluation and Review Technique (Pert) Method. Jurnal Sains dan Teknologi Tadulako, 9(1), 1–9.

Nanda, M. P., Kurniawati, M., & Riswanto, S. (2023). Penggunaan Metode Project Evaluation Review Technique (PERT) Dalam Evaluasi Perencanaan Penjadwalan Proyek. Jurnal Teknik Sipil, 17(3), 163–173. https://doi.org/10.24002/jts.v17i3.7181

Mayo-Alvarez, L., Alvarez-Risco, A., Del-Aguila-Arcentales, S., Sekar, M. C., & Yáñez, J. A. (2022). A Systematic Review of Earned Value Management Methods for Monitoring and Control of Project Schedule Performance: An AHP Approach. Sustainability, 14(22), 15259. https://doi.org/10.3390/su142215259

Pratiwi, A., Prihadi, W. R., & Al-Pashya, M. D. R. (2025). Cost and Time Performance Evaluation of a Sports Hall Construction Project Using the Earned Value Method: A Case Study at Gunung Kidul Campus, Universitas Negeri Yogyakarta. INERSIA: Informasi Dan Ekspose Hasil Riset Teknik Sipil Dan Arsitektur, 21(1), 91–101. https://doi.org/10.21831/inersia.v21i1.84089