PERCEPATAN JADWAL KONSTRUKSI DAN PENGARUHNYA TERHADAP BIAYA PENYELESAIAN PROYEK KONSTRUKSI
DOI:
https://doi.org/10.51988/vol1no1bulanjulitahun2020.v2i1.29Keywords:
minimum service standards, the exchange of money and time, accelerationAbstract
Means of transportation at present is very important to continue to be built effectively and efficiently to the level of fluency and accuracy of time toward the goal easier and faster and to meet minimum service standards of the highway. In line with that so that the toll road remain in the minimum service standards need to be additional road capacity to effectively and efficiently for that it is necessary to study whether the possible acceleration of road capacity expansion projects, so that the level of minimum service standards can be maintained and to what extent the effect of accelerating the schedule project on development costs.
One method that can be used to analyze the effect of accelerating the project towards the costs is to analyze the exchange of money and time (time cost trade off).
Variables used in the calculation of "Acceleration Schedule of Construction and Completion Costs Effect on Construction Project "is the direct labor, equipment, overtime working hours, method of construction, all have an influence on the different costs, acceleration (crash) or compression of time that have done the job and the biggest costs related to the work that has the greatest cost , a benefit if the toll road opened in advance of the acceleration due to a smaller project compared to the costs required for expediting the project construction on this project, based on the cost of the acceleration is not necessary because the costs to perform a greater acceleration when compared with a benefit.
References
Ahuja, Dozzi, and Abourizk (1994). Project Management: Techniques in Planning and Controlling Construction Projects, 2nd ed. New York: John Wiley & Sons.
Burke, Rory (1999). Project Managemen: Planning & Control Techniquest. 3rd ed. New York : John Wiley & Sons, Inc.
Departemen Pekerjaan Umum (1997) Manual Kapasitas Jalan Indonesia, Direktorat Jenderal Bina Marga, Jakarta.
Gould, Frederick E (1997). Managing the Construction Process: Estimating, Scheduling, and Project Control, 1st ed. New Jersey: Prentice-Hall, Inc.
Husen, Abrar (2009). Manajemen Proyek: Perencanaan Penjadwalan & Pengendalian Proyek, Edisi kesatu. Yogyakarta: Andi.
Kerzner, Harold (1995). Project Management. Seventh Edition. John Wiley & Sons, Inc. New York : McGraw-Hill.
Morlok, Edward K (1978). Introduction to Transportation Engineering and Planning. Tokyo : McGraw-Hill.
Santosa, Budi (2009). Manajemen Proyek: Konsep & Implementasi, Edisi kesatu. Yogyakarta: Graha Ilmu.
Soeharto, Imam (2001). Manajemen Proyek: Dari Konseptual sampai Operasional, Edisi kesatu. Jakarta: Erlangga.
Soeharto, Imam (2001). Manajemen Proyek: Dari Konseptual sampai Operasional, Edisi kedua. Jakarta: Erlangga.
Soekiman, A., Bangun, A.P., (2005), Peningkatan Daya Saing Kontraktor Melalui Optimasi Jadwal Penyelesaian Proyek, Jurnal Teknik Sipil, Universitas Katolik Parahyangan, Volume 6 Nomor 1, Juni, 2005
Pemerintah Republik Indonesia (2004), Undang-Undang No. 38 Tahun 2004 Tentang Jalan, Jakarta.
Yana, A.G., (2006), Pengaruh Jam Kerja Lembur Terhadap Biaya Percepatan Proyek Dengan Time Cost Trade Off Analysis, Jurnal Ilmiah Teknik Sipil, Universitas Udayana, Volume 10 Nomor 2, Juli, 2006
Venkataraman and Pinto (2008). Cost and Value Management in Projects, 1st ed. New York: John Wiley & Sons.
Downloads
Published
Issue
Section
License
Copyright (c) 2021 Jurnal Teknik Sipil Cendekia (JTSC)

This work is licensed under a Creative Commons Attribution 4.0 International License.











