COST AND TIME EVALUATION WITH TIME COST TRADE OFF (TCTO) METHOD IN TIJ TUNNEL CONSTRUCTION (JOYOBOYO INTERMODA TERMINAL)

Authors

  • Masca Indra Triana Program Studi Teknik Sipil Universitas 17 Agustus 1945 Surabaya
  • Ahmad Zaenul Baharnur Program Studi Teknik Sipil Universitas 17 Agustus 1945 Surabaya
  • Putri Suci Mawaritza Program Studi Teknik Sipil Universitas 17 Agustus 1945 Surabaya

DOI:

https://doi.org/10.51988/jtsc.v6i2.297

Keywords:

Cost and Time, Time Cost Trade Off (TCTO), Tunnel

Abstract

Infrastructure development is one of the main indicators in supporting city development, especially in metropolitan areas such as Surabaya. One of the strategic projects being designed is the construction of a pedestrian tunnel that will connect the Joyoboyo Intermodal Terminal (TIJ) with the Surabaya Zoo (KBS). This study aims to optimize the cost and completion time of the project through a case study of the construction of a pedestrian tunnel between TIJ and KBS. Based on the contract's provisions, this project is scheduled to be completed within 156 calendar days, starting on May 30 2024, and ending on November 21, 2024. As an effort to optimize the cost and duration of project implementation, the Time Cost Trade Off (TCTO) approach is used. Through the application of this method, the results obtained that the addition of working time (overtime) for 3 hours per day on the work item of reinforced concrete walls with a thickness of 60 cm and concrete quality Fc'35 MPa (PC 450) is quite effective in accelerating project completion from 156 days to 145 days. In addition, the optimum cost generated is Rp14,116,469,946.62, which means a cost saving of Rp43,510,269.42 compared to the normal cost. From the analysis results, the project time efficiency is 0.31%.

References

Desembardi, F., Fajar, M. N., Widodo, S., Tiara, L., Saputri, Y., Sipil, T., Sorong, U. M., No, J. P., & Sorong, K. (2024). Perbandingan Metode Percepatan Pekerjaan Terhadap Biaya Langsung dan Biaya Tidak Langsung pelaksaan proyek rencana dan lapangan , proyek untuk pengendalian agar suatu proyek dapat diatasi [ 13 ]. Salah satu agar proyek dapat selesai tepat waktu , pengguna. 16, 58–66.

Endriastuti, A. M., & Triana, M. I. (2024). Optimasi Biaya dan Waktu Dengan Metode TCTO pada Pembangunan Casting Mechanical & Civil Work For Oil Storage And Steady Room Workshop Gresik. Jurnal Teknik Industri Terintegrasi, 7(2), 1037–1048. https://doi.org/10.31004/jutin.v7i2.28837

Hudaya, R. G., Setiadji, J. S., Lesmana, A. L., Insinyur, P. P., & Petra, U. K. (2024). Analisis Profesionalisme Pada Proyek Konstruksi Restoran X di Bali. 2(September), 15–22.

Laras Titi Nawang Wulan, Isradinas Mirajhusnita, S. L. (2021). Analisis Optimasi Waktu Dan Biaya Dengan Penambahan Jam Kerja (Lembur) Menggunakan Metode Time Cost Trade Off. Teknik Sipil, 12(2), 47–56.

Mela, A. F. (2019). Analisis Time Cost Trade Off untuk Mengejar Keterlambatan Pelaksanaan Proyek Studi Kasus?: Pembangunan Hotel Zodiak Lampung, Pembangunan Hotel Park In By Radisson, Pembangunan Toko Mitra Hasil Sentosa di Bandar Lampung. Journal of Chemical Information and Modeling, 53(9), 1689–1699.

Muin, O. E. A. (2023). Cost and Time Analysis of the Pontianak Mcd Building Project Using Time Cost Trade Off (Tcto) Method. Asian Journal of Engineering, Social and Health, 2(12), 1733–1744. https://doi.org/10.46799/ajesh.v2i12.208

Nurabidin, M. R., & Beatrix, M. (2024). Optimasi Proyek Pembangunan Gedung Workshop Teknik Mesin Upn Veteran Jawa Timur Dengan Metode Time Cost Trade Off. Racic?: Rab Construction Research, 9(1), 158–169. https://doi.org/10.36341/racic.v9i1.4162

Rantung, C. C., Dundu, A. K. T., & Pratasis, P. A. K. (2020). Metode Pelaksanaan Konstruksi Pemasangan Atap Proyek Office and Distribution Centre , Pt . Sukanda Jaya Airmadidi – Minahasa Utara. Sipil Statik, 8(5), 687–694.

Saragi, T. E. (2022). Optimasi Waktu Dan Biaya Percepatan Proyek Menggunakan Metode Time Cost Trade Off Dengan Alternatif Penambahan Tenaga Kerja Dan Jam Kerja (Lembur) (Studi Kasus?: Pembangunan Gedung Convention Hall Kab. Deli Serdang). Construct?: Jurnal Teknik Sipil, 1(2), 53–69. http://repository.uhn.ac.id/handle/123456789/6146

Setiawan, I., Siboro, I., & Faisyal, M. (2021). Optimasi Waktu dan Biaya Proyek Menggunakan Metode Time Cost Trade Off (TCTO). Jurnal Ilmiah Teknik Sipil TRANSUKMA, 3(2), 114–128. https://doi.org/10.36277/transukma.v3i2.80