ANALISIS FAKTOR-FAKTOR PENYEBAB PEKERJAAN ULANG (REWORK) PADA PROYEK KONSTRUKSI BANGUNAN GEDUNG DI KOTA KUPANG

Authors

  • Gregorius Pius Usboko Program Studi Teknik Sipil, Fakultas Teknik, Universitas Katolik Widya Mandira Kupang
  • Sebastianus Baki Henong Program Studi Teknik Sipil Fakultas Teknik Unwira Kupang

DOI:

https://doi.org/10.51988/jtsc.v3i1.44

Keywords:

Rework, Building, Kupang City

Abstract

Implementation of a building construction project carried out through a certain management system. The project has a predetermined schedule and implementation plan. Common things that will occur if they are not in accordance with the schedule and implementation plan are delays in project implementation time and implementation costs. One of the factors causing the delay is due to rework activities on one or several items of construction work. The purpose of this study was to identify and analyze the factors that cause rework on building construction projects in the city of Kupang, East Nusa Tenggara Province. This study used a questionnaire instrument involving as many as 27 contractors, consisting of 12 site managers, 12 field implementers and 3 foreman. This research was conducted to see the dominant factor of rework in building construction projects in Kupang city. The results showed that the factors causing rework are known from managerial, design and resource factors which are the main causes of the emergence of rework in work. Operators working not according to procedures are one of the main causes of rework from the resource factor. Lack of teamwork is the cause of the rework of managerial factors. Unclear design or documentation is the cause of rework of design factors.

References

Dipohusodo, Istimawan. 1996. Manajemen Proyek dan Konstruksi. Yogyakarta : Kanisius

Erick, et al.,2014.Model dan Sumber Penyebab Rework pada Tahapan Proyek Konstruksi. Glasglow. Volume 3, No.4

Henong Sebastianus, 2016. Analisis Faktor-Faktor Yang Mempengaruhi Keterlambatan Pada Proyek Pemerintahan Di Kota Kupang. Prosiding Seminar Nasional Teknik Sipil, Fakultas Teknik Universitas Muhammadiyah Surakarta, 2016 ISSN: 2459-9727

Hidayat A, et al., 2010. Faktor-faktor Penyebab Pekerjaan Ulang (Rework) yang Berkaitan dengan Manajerial pada Proyek Konstruksi Jalan di Kabupaten Rokan Hulu.CED.Volume 1, No.1

Juliana H. Februari 2011. Kajian Pola Rework pada Pelaksanaan Pekerjaan Finishing Perumahan di Surabaya. Prosiding seminar nasional manajemen teknologi XIII. Volume 7, No.2.

Kukuh, et al., Juli 2011. Analisa Rework pada Konstruksi Gedung di Kabupaten Bondowoso. Prosiding seminar nasional manajemen teknologi XIV. Volume 8, No.1.

Nurhayati.2010. Manajemen Proyek. Graha ilmu : Medan

Prianto, Kusnul. 2012. Analisa Faktor Penyebab Pekerjaan Ulang pada Proyek Konstruksi di Kota Malang. Alfabeta. Volume 10, No.2.

Rahmatul, et al., Agustus 2012. Faktor-faktor Penyebab Pekerjaan Ulang (Rework) pada Pembangunan Gedung Dinas Bina Marga dan Cipta Karya Unsyiah. Pasca sarjana universitas syiah kuala. Volume 1, No.1.

Reksohadiprodjo, Sukanto.1983. Manajemen Proyek. Yogyakarta : BPFE

Ryan Ariefasa. Faktor Penyebab Keterlambatan Pekerjaan Konstruksi Bangunan Gedung Bertingkat yang Berpengaruh terhadap Perubahan Biaya pada Pekerjaan Struktur. Skripsi Program Sarjana Strata I Universitas Indonesia. Jakarta, 2012

Santosa, Budi. 2008. Manajemen Proyek. Surabaya : Graha Ilmu

Sugiyono.2013. Metode Penelitian Kombiinas. Bandung : Alfabeta

Sugiyono.2014.Metode Penelitian Pendidikan..Bandung : Alfabeta

Sugiyono. 2013. Statistika untuk Penelitian. Bandung : Alfabeta

Sutrisna, et al., Juli 2013. Analisis Rework pada Proyek Konstruksi Gedung di Kabupaten Bandung. Alfabeta. Volume 1, No.2

Yuni, et al., 2013. Faktor-faktor Penyebab Pekerjaan Ulang (Rework) pada Proyek Gedung di Kabupaten Rokan Hulu berdasarkan Persepsi Kontraktor.CED.Volume 1, No.1.